PERTH, AUSTRALIA--January 14, 2014--Researched by Industrial Info Resources Australia (Perth, Australia)--CITIC Pacific Mining Management Pty Limited (Perth, Australia) is preparing to perform the first A-class borescope maintenance on one of the gas turbines at the Sino Iron Power Station in April 2014. The station consists of seven 47-megawatt (MW), Siemens AG (NYSE:SI) SGT-800 combustion turbines, three steam turbines and associated heat-recovery steam generators (HRSG).